Cost Centres

Top  Previous  Next

Summary

Reports and jobs are easier to handle if broken into various areas or activities. These areas are called Cost Centres. To give more flexibility, you can have multiple sets of cost centres (called Cost Centre Banks).

 

Details

 

DM CC

 

Each Job in your system is assigned to one Cost Centre Bank, and therefore to a range of Cost Centres.

 

The choice of Cost Centres is somewhat arbitrary, but as a guide, use a different Cost Centre where you want:

       A different General Ledger Account

       A different Report Breakdown

       A different Purchase Order

       A different Schedule row (if using Job Control)

 

The Cost Centres Screen is divided into 2 sizable Panels:

 

Cost Centre Banks Grid

Where you can edit

Name
Default Income and expenditure GL accounts. These are only used if an individual cost centre does not have its own GL account set. They are used to prompt GL accounts when posting invoices

 

Cost Centres Grid

When you select a Cost Centre Bank, the Cost Centre table will display all the Cost Centres in that Cost Centre Bank.

You can edit

 

Name
Sort Order. The order Cost Centres appear on reports and grids. These can be set by drag & dropping, by setting Sort Order No or with the Arrange menu options
Expense and Income GL Accounts. These are used to prompt GL accounts when posting invoices. If not entered the default accounts of the parent Cost Centre Banks are used
Markup. When building Estimate Summaries, you can assign different markups to each cost centres as well as or instead of markups to the overall total Contract Proportion. When calculating progress claims based on work completed (invoiced), we need to establish what proportion of the contract is claimable
Sub Group. Cost centres can be grouped together in subgroups such as "Frame" or "Fit-out" to give shorter reports.
Pay Strategy. Feasibility Study and Job Control needs a default Pay Strategy (because suppliers may not yet be selected) to create cash flow reports based on when invoices will actually be paid.

 

Sub Groups

It is often useful to group certain cost centres together into sub groups such as "Frame" or "Fit-out" to give shorter reports, locate Cost Centres more readily and enhance estimating if you select View Sub Groups from the View menu, the lower panel changes to include sub-groups:

 

DM CCSubGroup

 

As you click on a sub group, only those cost centres in that sub group are shown. To set a cost centre, drag and drop it onto the desired sub group. Four command buttons are above the sub group grid:

 

               new        Create a new sub group

               Refresh        Refresh sub groups

               delete        Delete sub groups. Any cost centres in deleted sub groups are shifted to the unallocated sub group

               save        Save changes Do this after adding sub groups

 

 

Toolbar

 

       File Menu

               Import                        Imports cost centres from a csv file

               Export                        Exports cost centres to a csv file. Use this to transfer between companies or to view format

 

       Edit Menu

               Add a NEW Cost Centre

               Select All

               Set Default Markups        All selected Cost centres can be set to the same Markup

               Set to Subgroup                All selected Cost centres can be set to the same Subgroup

               Set to Pay Strategy        All selected Cost centres can be set to the same Pay Strategy

               Go to Cost Centre        

 

       View Menu                        Determines which grid columns are visible

               General Ledger

               Default Markup

               Sort Order

               Contract Proportion

               Sub Group                Shows Sub Groups

               Pay Strategy

 

       Arrange Menu                        Sets the order cost centres appear in reports etc

               By Alphabetical Code

               By Numeric Code

               By Cost Centre Name

               By Sub Group

               Calibrate Sort Order

 

       new        Creates a new Cost Centre Bank

       delete        Deletes the current or Selected Cost Centre Bank(s).Only empty banks can be deleted

       Supplier        Loads the Preferred Supplier Module

 

       new        Creates a new Cost Centre

       All_None        Select or deselect All cost centres

       delete        Deletes the current or Selected (s) Cost Centre

       copy        Copy Selected Cost Centres

       paste        Paste cost centre(s)

       report        Previews Report

       exit        Closes the routine