There are 2 different methods of viewing and manipulating Job Control data: Tree View and Grid/Chart. The differences between them can be summarized as follows:
Schedule
|
Grid/Chart
|
Simpler and faster
|
Slower and more cumbersome
|
Logic is more restricted:
You must start with a Milestone
You must end with another Milestone
Milestone activities must be in the root level.
All other activities must fall between adjacent milestones
Milestones have no duration (days are always zero)
|
The logic is more open ended. However you must nominate the relationship between all activities
|
Before and After activities are hidden and controlled by the system
|
You must specify Before and After activities
|
The system takes care of all logic
|
Setup is more cumbersome and it is possible to generate circular dependencies
|
Only the current activity details can be viewed
|
Multiple activities can be viewed at once
|
Completion dates calculated are the Latest possible dates
|
Completion dates calculated are the Earliest possible dates
|
A float is displayed ( the number of days up your sleeve before delays impact on the project
|
No float is available
|
Completions can be entered graphically via activity check boxes
|
Completions entry is more cumbersome
|
No Filter bar
|
Filter bar allows data searching
|
Tree can be collapsed and expanded
|
Filtering by filter bar and check boxes
|
Milestones and other activities can be inked to User Definable Dates. These dates can be linked to the Claim Schedule to automatically generate progress Claims
|
Not available
|
The 2 systems can operate side by side, but be aware that they will generate different results when refreshing schedules (mainly because of the different treatment of completion dates). The current tab in the main Index Tab determines the method: if the current tab is the grid, you get the old method
It is anticipated that the Tree method will in time replace the Grid/Chart option, which is still there for legacy reasons. It is possible to turn off user's access to the Grid/Chart method in Setup
This screen has 9 tabs:
Schedule Display a tree view of all activities for the current job and lets you modify their relationships
Suppliers Displays all suppliers, their outstanding orders and a Gantt chart of their commitments, including any clashes
Job Show Details for the current job
Notes Show diary notes for the current job
UDF Show User Definable Fields for the current job
Orders Lists all orders for the current job
Custom Reports
Grid Display a grid of all activities for the current job and lets you modify their relationships
Only visible if "View Grid" option is set in Setup/Users job control permissions tree
Chart Show the same data in a graphical Gantt chart format
Only visible if "View Chart" option is set in Setup/Users job control permissions tree
Toolbar
| Go to to Job Select a Job by Job Code |
| Refresh Data Refreshes all schedule data. Do this after making changes to underlying activities data such as action communiques etc |
| Add Date, time to Notes. Opens up the job Notes screen and Date and Time stamps it |
| Add Time to Notes. Opens up the job Notes screen and Time stamps it |
| Set Started. Sets the current (or selected) activity as Started |
| Set Completed. Sets the current (or selected) activity as Completed |
Activity Status Loads the Activity Status screen. Only available if the current tab is "Grid"
| Cascade Completions. The system scans the schedule and sets completions on any stage whose Before Code activity is complete |
| Set Actual to Target Menu Transfers values from actual to target |
| Lock Menu Locks the current (or selected) activity Dates. If Locked, dates are not adjusted when the schedule is refreshed |
| Unlock Menu Unlocks the current (or selected) activity Dates. If unlocked, dates are adjusted when the schedule is refreshed |
| Default Locking The current (or selected) activity Dates locks are set to the defaults as set in Setup. |
| Remove Unused. Any order activities in the current schedule that do not exist in the current job are deleted |
| Add missing. Any orders in the current job that do not appear in the schedule are added |
| Set Delivery Dates. Sets the delivery date on purchase orders based on projected start dates. |
| OK to Pay Selected Completed order activities have their OK to pay % set to 100%. If the invoice checking criteria in the parent Databuild system is set to Use OK to Pay, this can be used to authorise incoming invoices, or to generate pro_forma invoices from your suppliers and sub-contractors. |
| OK to Pay % Sets the OK to Pay % to an imput value on current or selected Activities, Orders or Grid Activities (based on current tab) |
| Add To Batch All orders whose After Milestone No is completed are added to the parent system's Order Batch, thus ensuring that all purchase orders are issued in time |
| Sort Menu | Only available if the current tab is either "Grid" or "Chart" |
Selects or Deselects all Jobs or Activities
Deletes the current (or Selected) Activity
Loads Feasibility Study module
Loads the Job Search module
Refreshes the current schedule
loads Reports screen
Email outstanding orders list to Suppliers. Enabled after running outstanding orders report
Loads the Macros module
Closes This module
|