A very useful part of Job Control that lets you assess the amount of work given to particular suppliers and whether your requirements place bottlenecks or clashes on them.
The upper part shows a tree view of all unfinished orders. If you have selected any jobs from the jobs grid at the left, the display will be restricted to those jobs. Otherwise all unfinished orders on all jobs are shown.
Command buttons
Clicking any supplier populates the lower chart, showing any unfinished orders for that supplier. Each row shows the available time range for the order (which cannot be moved without editing the schedule), and the activity time bar (which is moveable within the previously mentioned limits, unless of course there is no float)
The total number of days are shown below, with clashes (more than 1 day) shown in red.These are modified as you move the time bar