Schedule

Top  Previous  Next

Summary

The simplest way to run Job Control is to use the Tree View

 

 

Details

 

JC Main Tree

 

Activities on the current job are displayed, and can be manipulated using the command buttons:

 

       new        Add a new activity. This loads the Activities screen, where you can drag & drop Milestones, Actions, and Cost Centres

       delete        Deletes the selected activity and all activities below it.

       Up        Moves an activity UP the list

       Down        Moves an activity DOWN the list

       Left        Moves an activity to the LEFT, that is onto the same level as its parent

       right        Moves an activity to the RIGHT, that is UNDER the preceding activity

       Expand        Expands the tree so that all activities are visible

       Collapse        Collapses the tree so that only milestones are visible

       yes        Collapses and Expands the tree so that only incomplete activities are visible

       Contact        Declares child activities of completed activities to be also complete

       Audit        Declares parent activities of completed activities to be also complete

       Printer        Prints the tree

 

 

When an activity is selected (by clicking on it), a details block is displayed, containing:

 

Activity name, stage, dates, locks, days and float. Float is the number of days "up your sleeve" before delays to this activity impact on the overall project

 

Activity target dates, locks, days and float (if Show Targets is checked)

 

Comments, Action By Whom and UDF Date link. By Linking to a user definable date, rebuilding the schedule resets these dates which can be linked to the Claim Schedule to automatically generate progress Claims

 

OK to Pay details (if Show OK to Pay is checked)